Skyline Commercial Tower
Composite structural steel frame for a 22-storey commercial tower, fabricated and erected on a constrained city-centre site.
TONNAGE
2,400 T
FLOORS
22
PROGRAMME
34 weeks
GRADE
E350 / E450
YEAR
2024
The challenge
A tight urban plot with no laydown area and a fixed crane window meant steel had to arrive sequenced for just-in-time erection.
Our approach
We modelled the full frame in Tekla, fabricated in erection sequence, and ran a barcoded dispatch schedule so each lift landed in order.
The result
Zero site rework on connections and a frame topped out two weeks ahead of the contract programme.
Project data
- TONNAGE
- 2,400 T
- FLOORS
- 22
- PROGRAMME
- 34 weeks
- GRADE
- E350 / E450
Scope delivered
Client · Confidential — developer
Location · Mumbai, IN
Have a drawing? Let's forge it.