Harbour Road Bridge

Fabrication of welded steel plate girders for a four-lane road bridge, including camber and bolted field splices.

TONNAGE

1,650 T

SPAN

3 × 45 m

GIRDERS

welded plate

NDT

100% UT welds

YEAR

2023

Steel girders and beams forming a heavy industrial framework

The challenge

Deep welded plate girders required tight control of camber, distortion and full-penetration weld quality.

Our approach

Sequenced welding with pre-set camber on assembly beds and 100% ultrasonic testing of critical welds.

The result

All girders passed third-party inspection first time, with field splices bolting up to survey on site.

Project data

TONNAGE
1,650 T
SPAN
3 × 45 m
GIRDERS
welded plate
NDT
100% UT welds

Scope delivered

FabricationNDTMetalisingDelivery

Client · Confidential — infrastructure authority

Location · Kochi, IN

A molten metal pour throwing glowing orange sparks against a dark backdrop
START YOUR PROJECT

Have a drawing? Let's forge it.

Send us your drawings or a rough scope. We'll come back with a buildable quote, a programme, and a single point of contact.